#NameLength (km)Signing DateContract Sum (Bil)Stage
141SINGIDA - IGUGUNO34.0029/04/200514.769Completed
142BUZIRAYOMBO - GEITA100.0010/02/200541.14Completed
143IGUGUNU - SEKENKE33.0024/01/200513.65Completed
144SEKENKE - SHELUI33.0024/01/200519.093Completed
145TARAKE-RONGAI-KAMWANGA32.0016/09/200414.418Completed
146KYAMYORWA - BUZIRAYOMBO120.0001/04/200449.125Completed
147MOROGORO-DODOMA256.0022/03/2004256Completed
148MBWEMKURU - MINGOYO95.0024/02/200451.488Completed
149NZEGA-ISAKA-TINDE 73.0008/09/200320.61Completed
150TINDE-MWANZA/SHINYANGA BORDER96.0025/06/200328.25Completed
151NANGURUKURU - MBWEMKURU95.0014/02/200339.239Completed
152DODOMA - MANYONI127.0004/01/200363.888Completed
153SHELUI - NZEGA 112.0014/08/200220.723Completed
154SONGWE-TUNDUMA71.0027/10/200110.19Completed
155MUTUKULA-MUHUTWE112.0020/02/200113.84Completed
156DAR ES SALAAM - KIBITI60.0025/02/2021-Completed