#NameLength (km)Signing DateContract Sum (Bil)Stage
141UNITY BRIDGE1.0011/10/200524.678Completed
142SINGIDA - IGUGUNO34.0029/04/200514.769Completed
143BUZIRAYOMBO - GEITA100.0010/02/200541.14Completed
144IGUGUNU - SEKENKE33.0024/01/200513.65Completed
145SEKENKE - SHELUI33.0024/01/200519.093Completed
146TARAKE-RONGAI-KAMWANGA32.0016/09/200414.418Completed
147KYAMYORWA - BUZIRAYOMBO120.0001/04/200449.125Completed
148MOROGORO-DODOMA256.0022/03/2004256Completed
149MBWEMKURU - MINGOYO95.0024/02/200451.488Completed
150NZEGA-ISAKA-TINDE 73.0008/09/200320.61Completed
151TINDE-MWANZA/SHINYANGA BORDER96.0025/06/200328.25Completed
152NANGURUKURU - MBWEMKURU95.0014/02/200339.239Completed
153DODOMA - MANYONI127.0004/01/200363.888Completed
154SHELUI - NZEGA 112.0014/08/200220.723Completed
155SONGWE-TUNDUMA71.0027/10/200110.19Completed
156MUTUKULA-MUHUTWE112.0020/02/200113.84Completed
157DAR ES SALAAM - KIBITI60.0017/07/2019-Completed