#NameLength (km)Signing DateContract Sum (Bil)
61TABORA - URAMBO42.0030/07/201051.346
62NZEGA - TABORA58.8030/07/201066.358
63KYAKA - BUGENE59.1030/07/201064.96
64TABORA - NYAHUA85.0030/07/201093.402
65NYANGUGE - MUSOMA85.5030/07/201085.369
66MANYONI - ITIGI - CHAYA89.3030/07/2010109.643
67NDONO - URAMBO52.0030/07/201059.764
68UBUNGO TERMINAL, FEEDER STATION AND UP-COUNTRY BUS STATION-09/08/201014.674
69KARIAKOO TERMINAL AND FEEDER STATIONS-09/08/20106.348
70BAGAMOYO - MSATA64.0011/08/201089.608
71IKANA-LAELA64.2017/09/201076.076
72TUNDUMA-IKANA63.7022/09/201082.521
73WIDENING OF KILWA ROAD PHASE III1.5019/10/20105.482
74MALAGARASI BRIDGE AND APPROACH ROADS11.0021/10/201038.184
75KIVUKONI TERMINAL AND FEEDER STATION-21/10/20105.011
76MALAGARASI BRIDGE AND APPROACH ROADS37.0021/10/201036.67
77CHALINZE - TANGA120.0014/12/201067.237
78MBEYA - LWANJILO36.0017/12/201055.385
79JANGWANI DEPOT-24/12/201012.86
80FUFU ESCARP70.9013/01/201164.327